Acceptance

Acceptance is the buyer's documented decision that delivered parts meet the order, made against limits and methods agreed beforehand.

Every Acceptance article of the 3D Printing Resources, newest first, each written from published standards, research and makers’ data.

Meaning

Acceptance is the buyer’s documented decision that delivered parts meet the order, made against limits and methods agreed beforehand. ISO/ASTM 52901 gives it clause 4.5, which has 5 parts. They are general, qualification parts, the first production part, the final or reference part and the documentation of acceptance. Stricter requirements than the standard’s minimum are added at the time of the order.

Release Order

Qualification parts and witness specimens from the chosen parameter set show the process capable before the run. The first production part is inspected on every drawing feature and held for approval. A final or reference part is retained and marked as the comparison for later lots. The record of what was accepted, and when, closes the clause.
Read More

First Part Timing

The first production part is accepted before the rest of the run is built. A wrong orientation or parameter set costs least when found on the first part. In a worked case with assumed numbers, 600 parts arrive in 6 lots of 100, each compared with the reference part from lot 1. An inspection of “all lots” without a common reference lets an assumed drift of 0.1 % per lot compound to 0.5 % by lot 6. That drift uses the full selective laser sintering (SLS) and Multi Jet Fusion (MJF) band of ±0.5 % in one direction.

Acceptance Limits

Each dimension needs a limit, and a printed part’s limit depends on the process and the feature size. Formlabs publishes ±0.15 % for stereolithography (SLA) features of 1 to 30 mm (0.04 to 1.18 in), with a floor of ±0.02 mm (±0.0008 in). It gives ±0.5 % or 0.3 mm (0.012 in), whichever is larger, for SLS and MJF. A typical datasheet value is not an acceptance limit. The acceptance figure is written as a typical value or a lower bound, with its confidence level. A limit narrower than the process holds needs a step that delivers it, and the plan names that step.

Acceptable Imperfections

Clause 4.3.8 names acceptable imperfections and non-conformance, meaning what a part may show and still pass. For printed 316L, EOS reports an average defect percentage of 0.018 % from 45 samples on its 20 µm set. That figure is a reference point for the line. Support marks on resin are a feature of the process, and the drawing says which faces may carry them. A metal part cut from its plate without stress relief can come out of flat beyond the drawing. That failure traces back to the order of steps, which the order can fix in writing.

Documentation

Acceptance closes with a record of what was accepted and when, under clause 4.5.5. The record holds the inspection report, the build log and the specimen results, in a format the order names. A printed run’s record also lists the parts rejected and why. A mold maker starts from it when a tool takes over. The record costs little while the run is going and much more to rebuild later.

3D Printing Defects in a Production Batch Traced to Their Cause

A defect in a printed batch is traced by its pattern, every part, one zone, one build or a slow trend across builds, and each pattern points to its own cause and evidence.

Reading a Defect by Its Pattern Across the BatchThe 2022 review sorts the sources of metal powder bed defects into three groups: defects transferred from the feedstock powder, defects formed in the interaction of the beam with powder and metal during melting, and defects created in post-processing such as heat treatment. It adds a fourth set of contributors around them: the equipment, powder handling and dispensing, and build preparation, meaning orientation and supports.

Inspecting a 3D Printed Production Run and When a Mold Takes Over

Accept the first printed part against written limits, keep the record, and weigh a mold by identical quantity and design stability.

How a Printed Production Run Is Inspected and AcceptedISO/ASTM 52901:2017, titled requirements for purchased AM parts, gives the frame. Its scope says it covers the elements to be exchanged between customer and part provider at the time of the order: customer order information, part definition data, feedstock requirements, final part characteristics and properties, inspection requirements and part acceptance methods.

How Long a Batch of 3D Printed Parts Takes From Print to Pack-Out

A printed batch runs on four clocks, build, cooldown, finishing and inspection, and a stated lead time should show each.

Lead Time for a 3D Printed Batch Stage by StageThe calendar of a batch has the same skeleton in every process. Files are prepared and nested, the machine builds, the work cools or cures, parts are separated from what held them, and finishing and inspection follow.

Metal 3D Printing Stress Relief and Build Plate Removal Step by Step

Stress relieve metal parts on the plate, then cut, remove supports, anneal if needed and measure after the heat.

Metal Powder Bed Fusion Post-Build Steps in OrderThe post-build sequence for a part built on a plate has a stable shape across machine makers, because the stresses behave the same way. The sources agree on the order; they differ in how much of the detail they publish.

SLA Dimensional Tolerance by Feature Size

SLA tolerance is published as a percentage of feature size with a small floor, so a drawing writes bands and a post-cure condition and not one general figure.

SLA Tolerance Values Published by Two MakersTable 1 states the two specifications as their makers print them. Neither is a guarantee for a delivered part, and the Formlabs guide notes that the best way to judge a printer is to inspect real parts.

ISO/ASTM 52901 Requirements for Purchased Additive Manufactured Parts

The purchased parts standard lists what an additive parts order carries, from tolerances and feedstock to three acceptance stages, and leaves every value to the buyer.

What ISO/ASTM 52901 Asks a Buyer and a Supplier to ExchangeThe scope has three sentences and each one shapes how the standard is used. The first says the document defines and specifies requirements for purchased parts made by additive manufacturing.

Send the 3D File of Your Printed Part

Send the 2D drawing and the 3D file, with the quantity and the stage of the project. An engineer replies within 1 working day.

The quote form, the mutual NDA and the private folder for your files are on Protolis Atelier, with 3D Printing chosen.